Piled base Client - Scottish and Southern Electricity Networks

Task: To form a new Lucy switch base in poor ground conditions in minimal time.

We use a helical pile system, using air driven, hand carry-able tools to install bases in difficult to reach places. On this occasion, a failed switch meant this had to be installed as quickly as possible, minimising network outages. These bases are also available for unit subs and padmount subs. 


Previous
Previous

Lynes Common 132Kv grid site - Fencing works. Client - Scottish and Southern Electricity Networks

Next
Next

11Kv switch enclosures Client - Scottish and Southern Electricity Networks